The rain in June couldn’t dampened the determination of our amazing construction team to keep things moving ahead.

Approximately 120m3 of concrete was poured after a big vacuum cleaner was brought in to clean up the giant muddy puddle that was left behind from the storms that came through.

In July, 732.2 cubic metres of concrete have been installed, along with 110 tonnes of reinforcement for building D. The beams have also been installed for building D1, making it look less like a pile of dirt and more like the start of a building our students will be enjoying from next year.

We can’t wait to see what’s coming up next!